Following a successful competitive tendering process KKB was awarded the contract as Principal Contractor to carry out all the Remediation, Earthworks and Civil Engineering at Tarmac’s new flagship site,
The Contract consisted of;
Remediation and Earthworks
- Remediation of the former Tilbury Power Station which included complex sorting of 15000m3 of soil and removal of asbestos sporadically uncovered within the ground.
- 15,000m3 of Lime and Cement ex-situ stabilisation
- Import and Engineering of 8,000m3 of Sand
- Import and Engineering of 5,000m3 of 6N
- Import and Engineering of 10,000m3
- Excavation and Installation of 1000lm of open V Ditches
- Form 120,000m2 of the working platform with a Type 1 finish
- Form 15,000m2 of Piling platform
Client: Tarmac
Value: £1.5 million
Works: Remediation and Earthworks
Duration: 14 months
Completed: Ongoing